CASE STUDY

About the Client
° Global leader in the manufacturing of farm equipment, industrial equipment, lawn care equipment, diesel engines and drivetrain components
° Annual sales of 13 billion dollars
° Employs 45,000 associates

Project Statistics

° Duration: June 2000 to May 2001
° Number of resources: 6 consultants, 1 project manager
° Release: SAP R/3 version 4.6c
° Tools: On-Demand and Knowledge Warehouse
° Number of end users: 900

Delivered Services
° Project Management consulting for end user education initiative (initial purpose)
° Design and development of SAP Education Strategy
° Design and development of end user education materials
° Documentation translation
° Knowledge transfer to internal training resources

The teksoft Difference
° teksoft training professionals implemented teksoft Quality Assurance Process to ensure consistency and quality of BPPs and corresponding education materials
° Assisted client in cost-effective implementation of Knowledge Warehouse
° teksoft advised client on resource planning strategies to ensure client self reliance
° teksoft training professionals developed solid relationships with the client's internal training team
° Overall dedication to the project; for example, teksoft professionals worked overtime to create, assemble and test data in training application

Results
° On time!
° On budget
° Plant production at 80% of “pre-SAP” production levels within one week of “go-live” and 100% production within one month
° Significant cost reduction due to greater self reliance (example: a current SAP R/3 implementation was able to leverage training documentation from this engagement)